banner
News center
Quality and performance always take center stage in our products.

2024 Paving Season | Department of Streets | City of Philadelphia

Nov 01, 2024

Updated with paving or milling lists for the week of May 27, 2024.

The paving season is underway. The Streets Department plans to resurface 60 miles. Paving happens every year to keep our streets safe, smooth and return them to a state of good repair.

These streets are scheduled for the initial phases of improvement including milling, adjusting of manhole covers, and resetting of utility boxes. The separate activities take place over the course of the week. Operations for the milling work will be performed during day hours, between 7 A.M. and 4 P.M.

Check out this list of frequently asked questions.

When is paving season?Work begins late March/early April and continues through November.

How do I know if my street is on the paving list?The complete list of streets scheduled for repaving is at phila.gov/paving. You can also look for paving notifications posted on doors and/or vehicles in the affected area.

How long does it take a street to paved?The process takes three to five weeks from the time work begins. Exact time varies and is dependent on the length and width of the street.

Do I need to move my car during paving operations?Yes. There will be parking restrictions to allow crews to complete paving work. Temporary “No Parking” signs will say when cars should move. Moving your car prevents both towing and delays in the project.

What if my car is towed?If your car is towed, it will be towed to a nearby street. Contact your local Police District for the location of the car. A complete list of Police Districts can be found here.

How will I be notified about paving work?You are notified through the following means:

Where can I find the complete list of streets scheduled for paving?

You can view the complete list of streets scheduled for paving in the paving program booklet at phila.gov/paving.

Can the timeline for completed paving operations be altered?The normal paving timeline of three to five weeks can change depending upon weather conditions and area special events. Emergency utility work can also alter the paving schedule.

Will sidewalks be replaced during paving operations?New sidewalks are not included in paving operations. The city and/or its contractors are not responsible for any pre-existing damage. Each paving project is documented with photos before and after the project. If you need to report curb damage during repaving, please contact Philly311.

What is the paving process?

The street improvement process involves two separate phases or four steps:

When is paving season?How do I know if my street is on the paving list?How long does it take a street to paved?Do I need to move my car during paving operations?What if my car is towed?How will I be notified about paving work?DoorhangersTemporary “No Parking” signs.Updates on social media.Where can I find the complete list of streets scheduled for paving?Can the timeline for completed paving operations be altered?Will sidewalks be replaced during paving operations?What is the paving process?